Report: Cost of upgrading Flint's water plant rises to $108M

FLINT, MI (AP)--   A consultant says the cost of upgrading Flint's water treatment plant is estimated at $108 million, up slightly from an earlier estimate.

The Flint Journal says the recent report by engineering and construction company CDM Smith includes $37 million for the construction of two, 21-million gallon water storage tanks and more than $34 million for pump and transfer station upgrades.

A December draft report put the cost at $105 million.

Flint will treat Lake Huron water from a new pipeline. The plant improperly treated water from the Flint River in 2014-2015, leading to the city's crisis with lead-tainted water.

The report estimates work on the plant can be completed in 2019-2020. The state Department of Environmental Quality must agree to the final version of the consultant's report.

The Associated Press is one of the largest and most trusted sources of independent newsgathering, supplying a steady stream of news to its members, international subscribers and commercial customers. AP is neither privately owned nor government-funded; instead, it's a not-for-profit news cooperative owned by its American newspaper and broadcast members.